We had hoped that our next construction update would report a new transformer, completing the overall transformation, and an Open House date to celebrate. Alas, the new transformer install was delayed.
The backstory: The original electrical transformer is a dinosaur. Initially it was thought to suffice, particularly with our energy-efficient new systems. However, new considerations came up as the work moved forward, and it was determined that a new electrical transformer would be required after all. The County, PG&E and CalTrans are all involved, besides ourselves, our engineers and construction team.
Then, epic wild fires and winter storms made transformer work unsafe, and required transformers for recovery. Added to the local building boom, there have been unprecedented delays. We finally had an installation set in Feb. when the latest big storms hit, making work impossible on our date. We think we have a new date later in March, when the "storm door" hopefully closes, and crews are first available.
The transformer work happens overnight to minimize the impact on other businesses. Once the transformer is installed we can also return to our normal business hours. And we can throw a party!! The new transformer represents the completed transformation of the facility. We really can't wait.
There is some other good news to report. CalTrans and the county inspected and approved our underground work and allowed us to repave the portion of the road in front of the hospital. That work has been completed, so we continue to make good progress. In the meantime, we are enjoying working in the new hospital, and look forward to scheduling our open house to show you.